Route Optimisation Plant Setup

Paneldes requires you to input data you wish to analyse. You must have this data prepared before the route optimisation process can analyse it.

TIP: Before running routing functions, remove all of the route envelope construction.

Plant preparation

  • You must have created a plant model including all plant raceway, electrical equipment and enclosures. Your raceway network must conform to the cable connection distances that you have defined. I.e. try to avoid unintentional connection of components and raceway [due to proximity] and try to avoid missing connections.

  • Ensure cable filling factors are correctly applied to all of the raceway in your model.

  • Try to avoid LOOPING in your raceway network [This takes longer to calculate!]. i.e. Try to design an ARTERIAL network.